The groundwater barrier for the tunnel under the
new runway has been installed using a method known as jet grouting. Jet
grouting creates a cement wall below the ground surface surrounding the
entire excavation. The process is designed to dramatically reduce the
amount of groundwater getting into the construction site and therefore
to reduce the amount of water that has to be pumped away. As a result,
little if any impact to nearby groundwater levels is likely. To be absolutely
certain, the MAC has implemented an aggressive monitoring For further info go to; |